2.5 Hours
Before Automation
5 Minutes
After VBA Automation
2.42 Hours
Time Saved per month
Company Profile: It is an American multinational technology company headquartered in Armonk, New York, U.S with operation in 170 countries. It manufactures and markets computer hardware, middleware and software, and provides hosting and consulting services in area ranging from mainframe computers to nanotechnology.
Need for Automation:
The team announced Deep Dive(methodology) project at multiple levels to extract the key metrics for discussion. This project involves various analysis and huge time to gather all the information, process at each portfolio level and assess the scorecard to define the relevant information required to discuss. Automation in data collection, data processing and data presentation saves huge time and sort the essential metrics.
Cost-Benefit Analysis (Post Macro Implementation)
Description
AI Analysis
Frequency
4 Times
Time consumed manually
20 Minutes
Time Consumed for automated activity
1 Minutes
Total time savings per activity
Total time saved Per month
76 Minutes
Description
KPI’s Analysis
Frequency
1 Times
Time consumed manually
15 Minutes
Time Consumed for automated activity
1 Minutes
Total time savings per activity
Total time saved Per month
14 Minutes
Description
Scorecard Analysis
Frequency
1 Times
Time consumed manually
15 Minutes
Time Consumed for automated activity
Null
Total time savings per activity
Total time saved Per month
15 Minutes
Description
Overall Execution- Creation of Deck
Frequency
4 Times
Time consumed manually
10 Minutes
Time Consumed for automated activity
Null
Total time savings per activity
Total time saved Per month
40 Minutes
Description
Directors report –PS Unit
Frequency
8 Times
Time consumed manually
45 Minutes
Time Consumed for automated activity
10 Minutes
Total time savings per activity
35 Minutes
Total time saved Per month
280 Minutes
Description
To be approved hours report –PS Unit
Frequency
8 Times
Time consumed manually
20 Minutes
Time Consumed for automated activity
5 Minutes
Total time savings per activity
15 Minutes
Total time saved Per month
120 Minutes
Description
Line Manager Escalation Report- ITSPS Unit
Frequency
4 Times
Time consumed manually
180 Minutes
Time Consumed for automated activity
20 Minutes
Total time savings per activity
160 Minutes
Total time saved Per month
640 Minutes
Description
Line Manager Escalation Report – Time Management Unit
Frequency
4 Times
Time consumed manually
360 Minutes
Time Consumed for automated activity
75 Minutes
Total time savings per activity
285 Minutes
Total time saved Per month
1140 Minutes
Take 12-day session, and we will teach you how to Automate your Excel Reports and Processes using VB Programming and, save hours of work for you and the Company. You don’t need to know programming. All you should have is the adequate knowledge of Excel Functions.
Upcoming Schedule:
All our sessions are Classroom, Instructor-Led. If you feel, you need to assess your proficiency with Excel Formulae before reserving the seat, Schedule your pre-assessment with the support team at .
Throughout the course, you will be facilitated with 90 small-scale scenarios, 7case studies, and a Live VBA Project to implement the realtime automation back at work.